Good day Experts, I'm looking for a formula for a task running more than one month and need the % completion of each monthly update. For example, if a task is 140 days in duration start date is March 05 2023 and the Finish date is 15 Dec 2023, and Now the current date is Apr 30, 2023, and 15% of tasks are completed. how to calculate No of days achieved for the month of April 2023. just a note, I need these data to prepare a monthly S-curve using planned vs actual days of work. Thanks in Advance.