Hi...thank you all for what you do here...tremendous help to the rest of us! Anyway, I'm trying to create a project schedule for the renovation of certain parts of a building. The workdays are slated to be Saturdays, Sundays, Mondays, & Tuesdays only. However, on occasion there's a holiday on a Sat, Sun, Mon, or Tues. The information I have is a start date and an estimated number of days required for each renovation area.
So...clearly the workday function is out...looking at my current worksheet, I'm setup as the following...
D20: Quantity of work days required
E20: Start Date (03/19/2011)
F20: Finish Date (this would be start date + D20)
J19:J173: this is a list of all dates that are not work dates, mostly Wednesdays, Thursdays, Fridays, but it also includes some other days such as Mondays that are holidays, etc.
So...what I really really need is a formula for F20 that calculates the end date, but knows that the stuff in J19:J173 are not available as work dates...any ideas????
Thank you!
So...clearly the workday function is out...looking at my current worksheet, I'm setup as the following...
D20: Quantity of work days required
E20: Start Date (03/19/2011)
F20: Finish Date (this would be start date + D20)
J19:J173: this is a list of all dates that are not work dates, mostly Wednesdays, Thursdays, Fridays, but it also includes some other days such as Mondays that are holidays, etc.
So...what I really really need is a formula for F20 that calculates the end date, but knows that the stuff in J19:J173 are not available as work dates...any ideas????
Thank you!