MS Project quick help needed

hardcore1976

New Member
Joined
Jan 21, 2011
Messages
7
I need some quick help with a basic ms project file.

Its hard to explain in full detail but I'll give you an overview

Have 15 difference projects that i want to schedule together using the same resource pool

I know how many days each task will take and i basically want to enter a start date and have ms project fill in the rest. Can't seem to make this happen.

Any help would be greatly appreciated.
 
i think i'm using the tool incorrectly, i have each project as a task with subtasks for each of the tasks in each project and they are repetitive and i throughout all of them. Perhaps there is another way to do this. Appreciate any advice.
 
Upvote 0

Excel Facts

Return population for a City
If you have a list of cities in A2:A100, use Data, Geography. Then =A2.Population and copy down.

Forum statistics

Threads
1,225,537
Messages
6,185,513
Members
453,298
Latest member
Adam1258

We've detected that you are using an adblocker.

We have a great community of people providing Excel help here, but the hosting costs are enormous. You can help keep this site running by allowing ads on MrExcel.com.
Allow Ads at MrExcel

Which adblocker are you using?

Disable AdBlock

Follow these easy steps to disable AdBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the icon in the browser’s toolbar.
2)Click on the "Pause on this site" option.
Go back

Disable AdBlock Plus

Follow these easy steps to disable AdBlock Plus

1)Click on the icon in the browser’s toolbar.
2)Click on the toggle to disable it for "mrexcel.com".
Go back

Disable uBlock Origin

Follow these easy steps to disable uBlock Origin

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back

Disable uBlock

Follow these easy steps to disable uBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back
Back
Top