Hello,
I want to get one formula to get the 4th workday before end of month (not weekends)
I was trying with this formula, but is not working correctly (is showing 4/26 instead 4/25)
Example:
Thank You for your help.
I want to get one formula to get the 4th workday before end of month (not weekends)
I was trying with this formula, but is not working correctly (is showing 4/26 instead 4/25)
=DATE(YEAR(TODAY()), MONTH(TODAY()) + 1, 0) - 4
Example:
Month | 4th workday before end of month |
Apr | 25-Apr |
May | 28-May |
Jun | 25-Jun |
Jul | 26-Jul |
Aug | 27-Aug |
Sep | 24-Sep |
Oct | 28-Oct |
Nov | 26-Nov |
Dec | 26-Dec |
Thank You for your help.