How can I solve this WSM with NPV and ROI together?
25% net present value (NPV)
15% return on investment (ROI)
15% risk
20% strategic plan alignment
15% competition
10% resource availability.
Assume these NPVs:
Project 1: $3,640
Project 2: $62,360
Project 3: $101,270
Project 4: $52,820
Assume these ROIs:
Project 1: 2.92%
Project 2: 81.9%
Project 3: 44.5%
Project 4: 47.5%
25% net present value (NPV)
15% return on investment (ROI)
15% risk
20% strategic plan alignment
15% competition
10% resource availability.