Hello, I am new to this forum and hope someone can help me to understand how the Networkdays result is being calculated in my project.
I have created a calendar that uses the date function to store and display the day only value in a pictorial calendar.
Here is the start date - April 29, 2017
Here is the end date - May 5, 2017
I want to display the number of workdays between 4/29/2017 and 5/5/2017 - my expectation is to see the number "5"
However the result I get is -17.
I have no idea why. Can anybody help me?