Hi All,
First post here, everyday i have someone go around and record the hours on a machine kms or machine hours worked (SMU) i need to build a service register.
for example i have a lighting plant that needs a service every 250hrs and every 1000hrs a more indepth service, i currently have two columns saying minor service and major service
say this bit of machinery is currently at 8015hrs and i want to have the minor service column saying 8250hrs and the major service column saying 9000hrs
all my machinery is at different hours ie some are 100000 plus other under 5000 could someone help me out?
Cheers all
First post here, everyday i have someone go around and record the hours on a machine kms or machine hours worked (SMU) i need to build a service register.
for example i have a lighting plant that needs a service every 250hrs and every 1000hrs a more indepth service, i currently have two columns saying minor service and major service
say this bit of machinery is currently at 8015hrs and i want to have the minor service column saying 8250hrs and the major service column saying 9000hrs
all my machinery is at different hours ie some are 100000 plus other under 5000 could someone help me out?
Cheers all