I have a spreadsheet with a lot of data and I would like to calculate network days between column G and I, into column J, however, I would like to leave cell J blank if no date shows in Cell G or I is there a way around this, what im using is: =IFERROR(NETWORKDAYS(G2,I2),"")-1

Any help is much appreciated.
 

Excel Facts

Excel Can Read to You
Customize Quick Access Toolbar. From All Commands, add Speak Cells or Speak Cells on Enter to QAT. Select cells. Press Speak Cells.
How about
Excel Formula:
=IF(OR(G2="",I2=""),"",NETWORKDAYS(G2,I2)-1)
 
Upvote 0
You're welcome & thanks for the feedback.
 
Upvote 0

Forum statistics

Threads
1,223,246
Messages
6,170,996
Members
452,373
Latest member
TimReeks

We've detected that you are using an adblocker.

We have a great community of people providing Excel help here, but the hosting costs are enormous. You can help keep this site running by allowing ads on MrExcel.com.
Allow Ads at MrExcel

Which adblocker are you using?

Disable AdBlock

Follow these easy steps to disable AdBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the icon in the browser’s toolbar.
2)Click on the "Pause on this site" option.
Go back

Disable AdBlock Plus

Follow these easy steps to disable AdBlock Plus

1)Click on the icon in the browser’s toolbar.
2)Click on the toggle to disable it for "mrexcel.com".
Go back

Disable uBlock Origin

Follow these easy steps to disable uBlock Origin

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back

Disable uBlock

Follow these easy steps to disable uBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back
Back
Top