Network days

xxsalahxx

Active Member
Joined
Jun 25, 2011
Messages
320
Office Version
  1. 2007
Hello
I have a spreadsheet with a lot of data and I would like to calculate network days between column G and I, into column J, however, I would like to leave cell J blank if no date shows in Cell G or I is there a way around this, what im using is: =IFERROR(NETWORKDAYS(G2,I2),"")-1

Any help is much appreciated.
 

Excel Facts

Quick Sum
Select a range of cells. The total appears in bottom right of Excel screen. Right-click total to add Max, Min, Count, Average.
How about
Excel Formula:
=IF(OR(G2="",I2=""),"",NETWORKDAYS(G2,I2)-1)
 
Upvote 0
You're welcome & thanks for the feedback.
 
Upvote 0

Forum statistics

Threads
1,224,825
Messages
6,181,189
Members
453,020
Latest member
Mohamed Magdi Tawfiq Emam

We've detected that you are using an adblocker.

We have a great community of people providing Excel help here, but the hosting costs are enormous. You can help keep this site running by allowing ads on MrExcel.com.
Allow Ads at MrExcel

Which adblocker are you using?

Disable AdBlock

Follow these easy steps to disable AdBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the icon in the browser’s toolbar.
2)Click on the "Pause on this site" option.
Go back

Disable AdBlock Plus

Follow these easy steps to disable AdBlock Plus

1)Click on the icon in the browser’s toolbar.
2)Click on the toggle to disable it for "mrexcel.com".
Go back

Disable uBlock Origin

Follow these easy steps to disable uBlock Origin

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back

Disable uBlock

Follow these easy steps to disable uBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back
Back
Top