Hello,
Ive set up a tracking document which allows me to see the final date an order can be placed without causing further impact. However what im wanting to happen, is when the item has been actioned, it will stop the countdown of days
Lead Time (D) - how long the material is on
Required on site (F) - Date needed
Final Bulk Order Date (G) - =F8-D8
Countdown (I) - =G8-TODAY()
My idea is that if in column J has a status entered into it i.e. "Complete" it will stop column I counting down further. If it "Pending" it will continue to count down
Thanks
Ive set up a tracking document which allows me to see the final date an order can be placed without causing further impact. However what im wanting to happen, is when the item has been actioned, it will stop the countdown of days
Lead Time (D) - how long the material is on
Required on site (F) - Date needed
Final Bulk Order Date (G) - =F8-D8
Countdown (I) - =G8-TODAY()
My idea is that if in column J has a status entered into it i.e. "Complete" it will stop column I counting down further. If it "Pending" it will continue to count down
Thanks
Element of Works (C) | Lead Time (Mat + Fab) (D) | Required on Site (F) | Final Bulk Order Date (G) | Outstanding Info (H) | Countdown (I) | Status (J) |
Terracotta Tiles (Smooth) | 126 | 03-Jan-24 | 23-Aug-23 | C | 2.00 | Complete |
Terracotta Tiles (Profiled) | 126 | 03-Jan-24 | 23-Aug-23 | C | 2.00 | Pending |