ms project days from finish

iknowu99

Well-known Member
Joined
Dec 26, 2004
Messages
1,158
Office Version
  1. 2016
i'm looking to have a column in ms project that will reflect the days for the even that are left

so like

advertising is task name and now i have duration as the column managing the time line....can i make it not duration but like time from project completion?

because there is a specific date the project must be completed by and advertising should be done with it 15 days before that....
 

Excel Facts

Square and cube roots
The =SQRT(25) is a square root. For a cube root, use =125^(1/3). For a fourth root, use =625^(1/4).

Forum statistics

Threads
1,225,478
Messages
6,185,228
Members
453,283
Latest member
Shortm88

We've detected that you are using an adblocker.

We have a great community of people providing Excel help here, but the hosting costs are enormous. You can help keep this site running by allowing ads on MrExcel.com.
Allow Ads at MrExcel

Which adblocker are you using?

Disable AdBlock

Follow these easy steps to disable AdBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the icon in the browser’s toolbar.
2)Click on the "Pause on this site" option.
Go back

Disable AdBlock Plus

Follow these easy steps to disable AdBlock Plus

1)Click on the icon in the browser’s toolbar.
2)Click on the toggle to disable it for "mrexcel.com".
Go back

Disable uBlock Origin

Follow these easy steps to disable uBlock Origin

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back

Disable uBlock

Follow these easy steps to disable uBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back
Back
Top