Hello,
I need a formula that will convert calendar days to workdays. I only have the start date and number of calendar days. I would then add the workdays to the start date to determine the actual end date. From there I would add one business day to provide the next start date using the same number of calendar days to determine the next end date. I don't have the info required to use either the workday or network days function. Any assistance would be appreciated.
I need a formula that will convert calendar days to workdays. I only have the start date and number of calendar days. I would then add the workdays to the start date to determine the actual end date. From there I would add one business day to provide the next start date using the same number of calendar days to determine the next end date. I don't have the info required to use either the workday or network days function. Any assistance would be appreciated.