dineshtendulkar
Board Regular
- Joined
- Apr 18, 2011
- Messages
- 53
Description Quantity Start Date Finish Date Jan-10 Feb-10
1 2 3 4 1 2 3 4
Excavation 100 05-01-10 14-01-10 30 70
Hi friends,
I am having an excel spreadsheet as shown above. I have splitted every month into 4 weeks..
1 - 7 = First Week
8-14 = Second Week
15 - 21 = Third Week
22 - 28, 30 or 31 = Fourth Week
What I need now is to Split-up the Quantity as per the Start Date and Finish Date as shown above.
I badly need this formula.. Searched in google I cant able get it. Any Experts Please Help Me
Additional Information
For Example, If i am doing Excavation Activity and if its quantity is 100, the start date is 05-Jan-2010 and Finish Date is 14-Jan-2010
Here we are considering 1-7th of Every month as First Week, but the activity starts on 5th January 2010, So in the first week we have the duration of 3 days and it ends on 14th January 2010, so the second week has the duration of 7 days, so the total duration is 10 days, it should divide the quantity as Total Quantity/total duration and should split the total quantity into weekwise distribution. In this example, for first week 3 days duration so in the first week it should fill (100/10)*3 and in the second week the duration is 7 days and so it should fill as (100/10)*7.
Also you should consider that we are everymonth into 4 weeks. For February month, the last
week will have a duration of 7 days, whereas January, March, May, July, August, October, December will have a duration of 10 days in the last week and April, June, September, November will have a duration of 9 days.
Consider other examples such as,
For example, the total quantity of concrete is 500 and the start date is 22-January-2010 and its finish date is 4-April-2010.
Then it should split the quantity as follows,
January 4th Week = 68.49315
February 1st Week = 47.94521
February 2nd Week = 47.94521
February 3rd Week = 47.94521
February 4th Week = 47.94521
March 1st Week = 47.94521
March 2nd Week = 47.94521
March 3rd Week = 47.94521
March 4th Week = 68.49315
April 1st Week = 27.39726
I think now you better understood my question, I am waiting for your reply boss....
1 2 3 4 1 2 3 4
Excavation 100 05-01-10 14-01-10 30 70
Hi friends,
I am having an excel spreadsheet as shown above. I have splitted every month into 4 weeks..
1 - 7 = First Week
8-14 = Second Week
15 - 21 = Third Week
22 - 28, 30 or 31 = Fourth Week
What I need now is to Split-up the Quantity as per the Start Date and Finish Date as shown above.
I badly need this formula.. Searched in google I cant able get it. Any Experts Please Help Me
Additional Information
For Example, If i am doing Excavation Activity and if its quantity is 100, the start date is 05-Jan-2010 and Finish Date is 14-Jan-2010
Here we are considering 1-7th of Every month as First Week, but the activity starts on 5th January 2010, So in the first week we have the duration of 3 days and it ends on 14th January 2010, so the second week has the duration of 7 days, so the total duration is 10 days, it should divide the quantity as Total Quantity/total duration and should split the total quantity into weekwise distribution. In this example, for first week 3 days duration so in the first week it should fill (100/10)*3 and in the second week the duration is 7 days and so it should fill as (100/10)*7.
Also you should consider that we are everymonth into 4 weeks. For February month, the last
week will have a duration of 7 days, whereas January, March, May, July, August, October, December will have a duration of 10 days in the last week and April, June, September, November will have a duration of 9 days.
Consider other examples such as,
For example, the total quantity of concrete is 500 and the start date is 22-January-2010 and its finish date is 4-April-2010.
Then it should split the quantity as follows,
January 4th Week = 68.49315
February 1st Week = 47.94521
February 2nd Week = 47.94521
February 3rd Week = 47.94521
February 4th Week = 47.94521
March 1st Week = 47.94521
March 2nd Week = 47.94521
March 3rd Week = 47.94521
March 4th Week = 68.49315
April 1st Week = 27.39726
I think now you better understood my question, I am waiting for your reply boss....