Hello,
I am need of a formula to calculate the following:
Work order started: 1/1/2018
Time 7:00am
Work Order Completed: 1/3/2018
Time 11:00pm
The issue I have is that from 11:00pm to 7:00am, we do not have an operating shift.
I am looking to calculate how much time is being spent on work orders without the hours of 11:00pm to 7:00am being added to the total overall time.
How can I accomplish this?
Thank you!
I am need of a formula to calculate the following:
Work order started: 1/1/2018
Time 7:00am
Work Order Completed: 1/3/2018
Time 11:00pm
The issue I have is that from 11:00pm to 7:00am, we do not have an operating shift.
I am looking to calculate how much time is being spent on work orders without the hours of 11:00pm to 7:00am being added to the total overall time.
How can I accomplish this?