I need to calculate throughput by quarter for a project, based on units created.
For example:
There 432 total widgets needed;
22 widgets can be completed a week;
how many widgets can be completed by quarter until all 432 widgets are done
with a start date of 5/1/19.
Can someone help and provide me a formula?
Thank you!