Hi,
I am trying to create a tricky formula and have come close twice but not exactly what I need, maybe you could help?
I have a quantity of hours (project) that needs to have a specific start and end date. Then that quantity of hours between specific dates needs to be spread across specific months.
1st problem- The months start and end dates aren't exactly as per the generic calendar so must be specified in a separate cell.
2nd problem- a value in a different cell defines how many hours can be burnt from the project total per day.
3rd problem- The formula must realise that Mon- Fri are full working days but Sat and Sunday are 1/4 of the full working day capacity/burn rate.
4th Problem- The formula must also recognise holidays when all operations are shutdown (typically 10days over Christmas period depending on calendar days and how they fall)
Example:
A project has a total of 7,700 hours. To be worked at full capacity Monday-Friday, 1/4 capacity Saturday and Sunday and excluding holiday shutdown (23/DEC/23 - 01/JAN/24).
The project start is 14/DEC/24 and the end date is 19/JAN/24 (7700 hrs must be spread between these dates according to the capacity burn on ITEM 3=330 hrs a day but must also account for the calendar start/ends as well as including holiday shutdown days(all seen in this message))
The capacity hours that can be burnt in a day are set values depending on which item type is being worked on. IF item 3=330hrs per day, item A=325, item 5=420, item 6=450 , item 8= 275 & item PL=100.
Calendar start end dates are as follows:
DEC start= 28/NOV/23.
DEC end= 31/DEC/23 (no working days from/to 23/12/23 - 01/01/2024, last day of work is 22nd DEC).
JAN start= 01/JAN/24 (no working days on the 01/JAN/24) so actual start is the 2nd JAN.
JAN end= 31/JAN/24.
Maybe you could suggest a formula for these parameters??
I've tried a couple of ways that seem to be almost correct but they are not 100% and I need better accuracy. For example I had two projects of 7,700 on item 3 (daily burn 330hrs) that start in December ( one on the 14-DEC and the other on the 17-DEC) and they both end on JAN 19th. However the hours allocated in January aren't the same because the formula I use breaks the total hours between months as a percentage of 100 so while January should be the same (because it has the same possible amount of days to burn daily hours) it is different because my formula spreads more hours into December due to the earlier start date.
I tried to attach a picture of this explanation but I cant paste into this message box or attach elsewhere. I'd be happy to have a video call to show visually if that helps.
I am trying to create a tricky formula and have come close twice but not exactly what I need, maybe you could help?
I have a quantity of hours (project) that needs to have a specific start and end date. Then that quantity of hours between specific dates needs to be spread across specific months.
1st problem- The months start and end dates aren't exactly as per the generic calendar so must be specified in a separate cell.
2nd problem- a value in a different cell defines how many hours can be burnt from the project total per day.
3rd problem- The formula must realise that Mon- Fri are full working days but Sat and Sunday are 1/4 of the full working day capacity/burn rate.
4th Problem- The formula must also recognise holidays when all operations are shutdown (typically 10days over Christmas period depending on calendar days and how they fall)
Example:
A project has a total of 7,700 hours. To be worked at full capacity Monday-Friday, 1/4 capacity Saturday and Sunday and excluding holiday shutdown (23/DEC/23 - 01/JAN/24).
The project start is 14/DEC/24 and the end date is 19/JAN/24 (7700 hrs must be spread between these dates according to the capacity burn on ITEM 3=330 hrs a day but must also account for the calendar start/ends as well as including holiday shutdown days(all seen in this message))
The capacity hours that can be burnt in a day are set values depending on which item type is being worked on. IF item 3=330hrs per day, item A=325, item 5=420, item 6=450 , item 8= 275 & item PL=100.
Calendar start end dates are as follows:
DEC start= 28/NOV/23.
DEC end= 31/DEC/23 (no working days from/to 23/12/23 - 01/01/2024, last day of work is 22nd DEC).
JAN start= 01/JAN/24 (no working days on the 01/JAN/24) so actual start is the 2nd JAN.
JAN end= 31/JAN/24.
Maybe you could suggest a formula for these parameters??
I've tried a couple of ways that seem to be almost correct but they are not 100% and I need better accuracy. For example I had two projects of 7,700 on item 3 (daily burn 330hrs) that start in December ( one on the 14-DEC and the other on the 17-DEC) and they both end on JAN 19th. However the hours allocated in January aren't the same because the formula I use breaks the total hours between months as a percentage of 100 so while January should be the same (because it has the same possible amount of days to burn daily hours) it is different because my formula spreads more hours into December due to the earlier start date.
I tried to attach a picture of this explanation but I cant paste into this message box or attach elsewhere. I'd be happy to have a video call to show visually if that helps.