Seafox
New Member
- Joined
- Jun 9, 2021
- Messages
- 7
- Office Version
- 365
- Platform
- Windows
I'm looking for some help on making a recover calculation for a glide path. Example being I have 12 weeks to get 120 items out by. if I miss a week I need the calculation to give me the run rate for the remaining weeks in in each of the remaining weeks. as per the basic typed example below.
Thanks in advance
Thanks in advance
1 | A | B | C | D | E | F | G | H | I | J | K | L | M | N |
2 | 01/01/2024 | 08/01/2024 | 15/01/2024 | 22/01/2024 | 29/01/2024 | 05/02/2024 | 12/02/2024 | 19/02/2024 | 26/02/2024 | 04/03/2024 | 11/03/2024 | 18/03/2024 | Totals | |
3 | RQD | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 120 |
4 | Actual | 0 | 0 | 0 | ||||||||||
5 | Recovery Glide | 12 | 12 | 12 | 12 | 12 | 12 | 12 | 12 | 12 | 12 | 120 |
Last edited: