PMS Report - E3406 | 25.02.2025 | ||
Target | Achievment | Balance | Required /Day |
120 | 77 | 43 | 7.00 |
Date is on D1
target value for the month in on A3
Acheivement as on date is on B3
Balance target is on C3 (A3-B3)
Required Per Day in on D3.
I have a formula on D3 is =ROUNDUP(C3/(EOMONTH(D1,0)-D1-SUMPRODUCT(-(WEEKDAY(ROW(INDIRECT(EOMONTH(TODAY(),-1)+1&":"&EOMONTH(TODAY(),0))))=1))),0)
as per formula the per day requirement to achieve the target is showing 7
but as only 3 days left to end February Month. as per balance target the per day requirement should be 15 (roundup value), but it showing 7
please correct the formula or provide another formula
regards
Dinesh