I am working with an Excel sheet that tracks project efforts across multiple roles (e.g., Senior Designers, Junior Designers) for each month. The goal is to calculate the total effort needed for each role, factoring in the backlog as well, the calculations should assume that the backlog items would start in on the month of the calculation, for example even though Project 6 can start in Feb-25 I still need to show that in Dec-24 project 6 would still potentially consume 30 days if it were to start in Dec-24. you should note that in Jan-25 I should count the data from Month 2 for a project that started in Dec-24 etc
Here's the link to the file.
I need the calculations to be added to the yellow-highlighted columns from the Monthly Calculations.
As mentioned previously, I have a project (e.g., Project 10) that may start at a later date, such as in April. However, I want the calculation for the required effort in Month 1 of Project 10 to be displayed in December, January, February, and March, since the project hasn't started yet. If it does start later, we would need to account for Month 1's efforts.
Thank you in advance.
Here's the link to the file.
I need the calculations to be added to the yellow-highlighted columns from the Monthly Calculations.
As mentioned previously, I have a project (e.g., Project 10) that may start at a later date, such as in April. However, I want the calculation for the required effort in Month 1 of Project 10 to be displayed in December, January, February, and March, since the project hasn't started yet. If it does start later, we would need to account for Month 1's efforts.
Thank you in advance.