Hi guys can someone help me solve these problems
Pricing
Below are the costs to source and sell a laptop cooling pad on Amazon.
Calculate
Production and shipment planning
You are required to decide the next purchase order (PO) for a gaming keyboard with the information below. Feel free to make any assumptions necessary.
A. Stock situation
Minimum order quantity - 1000 units
Order schedule - POs are placed once every 30 days
Shipment timelines
Transit time from factory in China to Amazon - 45 days
Questions
Pricing
Below are the costs to source and sell a laptop cooling pad on Amazon.
- Purchase cost - 7.49€
- Ocean freight - 1.03€
- Amazon commission - 15% of selling price
- Order fulfilment fees - 3.99€
- Storage fees - 0.15€
- Average PPC (advertising) spend - 8% of selling price
- VAT - 20%. The selling price should be inclusive of VAT. For example if the VAT inclusive price of a product is 120€, the customer pays 120€ which includes the 20% VAT 20€. Net proceeds for the seller will be 100€.
Calculate
- the ideal price to meet target margins of 18-22% and,
- the breakeven price
Production and shipment planning
You are required to decide the next purchase order (PO) for a gaming keyboard with the information below. Feel free to make any assumptions necessary.
A. Stock situation
Stocks at Amazon - 1 Mar 2021 | 2241 units |
Daily velocity based on the last 30 days | 28 units |
In production - completion date 28 Mar 2021 | 1500 units |
- Production timelines
Minimum order quantity - 1000 units
Order schedule - POs are placed once every 30 days
Shipment timelines
Transit time from factory in China to Amazon - 45 days
- Past sales history
Mar 20 | Apr 20 | May 20 | Jun 20 | Jul 20 | Aug 20 | Sep 20 | Oct 20 | Nov 20 | Dec 20 | Jan 21 | Feb 21 | |
Total Sales | €22,655 | €22,655 | €20,228 | €20,228 | €20,228 | €20,228 | €22,655 | €24,273 | €43,691 | €68,774 | €29,128 | €22,655 |
Total Units | 840 | 840 | 750 | 750 | 750 | 750 | 840 | 900 | 1620 | 2550 | 1080 | 840 |
Daily Velocity | 28 | 28 | 25 | 25 | 25 | 25 | 28 | 30 | 54 | 85 | 36 | 28 |
Questions
- When will you place the next PO?
- What would be the PO quantity?
- Explain your reasoning and state any assumptions you made to arrive at your decision.
- What additional information would be relevant to make a better decision?
- Do you have any proposals to improve the supply chain?