Hello I am trying to calculate month end dates, however should be weekend dates (Saturday being weekend) based on previous week end dates, Please see below example
At any point I will have rolling 52 weeks. Col Z is the 52th week ending date in July 06/07/24 , thereafter in cell C5 the date should be automatically calculated as following month end date , however that should be week end date.
Next I also want that the total weekly sales should be updated against following year's month end date calculated as per above. e.g.
Sum(15/07/23 + 22/07/23 + 29/07/23 + 05/08/23) = 22 , update in Week end date 03/08/24 and so on...
So looking for help on how to setup above dynamically so that when the week end dates chnage , the month end dates get calcuated along with values.
Many thanks in advance.
At any point I will have rolling 52 weeks. Col Z is the 52th week ending date in July 06/07/24 , thereafter in cell C5 the date should be automatically calculated as following month end date , however that should be week end date.
Next I also want that the total weekly sales should be updated against following year's month end date calculated as per above. e.g.
Sum(15/07/23 + 22/07/23 + 29/07/23 + 05/08/23) = 22 , update in Week end date 03/08/24 and so on...
So looking for help on how to setup above dynamically so that when the week end dates chnage , the month end dates get calcuated along with values.
Many thanks in advance.