Calculate dates while excluding Sundays

DroZ3

New Member
Joined
Mar 22, 2018
Messages
22
Office Version
  1. 365
Platform
  1. Windows
Hi,

On a construction project, I need to calculate a bunch of milestones dates from a start date BUT the dates need to be calculated based on a 6-days work week which would exclude SUNDAYs.
Is there a function for that ?
I know about NETWORKDAYS but it excludes both Saturday and Sunday ... I only want to exclude Sundays.

Thanks for the help.
 

Excel Facts

How can you turn a range sideways?
Copy the range. Select a blank cell. Right-click, Paste Special, then choose Transpose.
You can use the networkdays.intl function & for the weekend argument use 11
 
Upvote 0
Glad we could help & thanks for the feedback.
 
Upvote 0

Forum statistics

Threads
1,223,911
Messages
6,175,324
Members
452,635
Latest member
laura12345

We've detected that you are using an adblocker.

We have a great community of people providing Excel help here, but the hosting costs are enormous. You can help keep this site running by allowing ads on MrExcel.com.
Allow Ads at MrExcel

Which adblocker are you using?

Disable AdBlock

Follow these easy steps to disable AdBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the icon in the browser’s toolbar.
2)Click on the "Pause on this site" option.
Go back

Disable AdBlock Plus

Follow these easy steps to disable AdBlock Plus

1)Click on the icon in the browser’s toolbar.
2)Click on the toggle to disable it for "mrexcel.com".
Go back

Disable uBlock Origin

Follow these easy steps to disable uBlock Origin

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back

Disable uBlock

Follow these easy steps to disable uBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back
Back
Top