Hi all
I am looking for some help, regarding trying to calculate the next Tuesday following a certain date.
If I explain the process it might be easier, currently we have a multi stage (7 in total), process that is connected to the previous stage, and 3 of these stages can only happen on a Tuesday, the other 7 must happen on a workday (Mon to Fri) excluding bank holidays, which is simple enough using the WORKDAY function and a list of dates for the bank holidays.
Start Date Number of process days (working only) Next Progress working Date Next Progress Tuesday Date19/03/2018 7 28/03/2018 03/04/2018
How do we calculate the next progress Tuesday date, plus as an added complication, what happens if the next Progress date lands on a bank holiday so this would need to find the next non bank holiday.
I hope I have explained this ok, I'm looking for any ideas you might have.
Thank you and regards
Ian
I am looking for some help, regarding trying to calculate the next Tuesday following a certain date.
If I explain the process it might be easier, currently we have a multi stage (7 in total), process that is connected to the previous stage, and 3 of these stages can only happen on a Tuesday, the other 7 must happen on a workday (Mon to Fri) excluding bank holidays, which is simple enough using the WORKDAY function and a list of dates for the bank holidays.
Start Date Number of process days (working only) Next Progress working Date Next Progress Tuesday Date19/03/2018 7 28/03/2018 03/04/2018
How do we calculate the next progress Tuesday date, plus as an added complication, what happens if the next Progress date lands on a bank holiday so this would need to find the next non bank holiday.
I hope I have explained this ok, I'm looking for any ideas you might have.
Thank you and regards
Ian